OUR REFERENCES - Floating Cranes
NEW BRIDGE INSTALLED IN ROUEN
August 2006
New bridge installed in Rouen
New bridge installed in Rouen
During the month of August 2006, two giant floating cranes came especially from Rotterdam to Rouen to lift and install various heavy elements of the new bridge « Gustave Flaubert ».
The sheerlegs « Taklift 7 » and « Matador 3 » lifted pieces weighing between 500 and 1200 tons each.
The 2 central decks of this new road bridge can be lifted high to let sea going vessels pass under the bridge and reach the port of Rouen.
LAUNCHING OF THE PARIS FLOATING SWIMMING POOL
June 2005
LAUNCHING OF THE PARIS FLOATING SWIMMING POOL
Build on a quay in few concrete sections weighing up to 1150 tons each at
Rouen, the new swimming pool of Paris has smoothly been launched in June
2005 into the Seine river water. This was carried out using "Taklift 4"
with a special rigging arrangement to prevent excessive load stress in the
concrete structure. The swimming pool sections thereafter have been pushed
on the river and through the locks upto the city of Paris for further assembly.
Lifting and installation of a pedestrian bridge across the Loire river in the city of Nantes.
June 2001
Lifting and installation of a pedestrian bridge across the Loire river in the city of Nantes.
In June 2001 the sheerleg "Taklift 3" proceeded to the installation of the various
spans of a pedestrian bridge over the Loire river arm connecting the justice
building to the city centre of Nantes. The use of the sheerleg's jib
was required to allow to pick up the pieces from their assembly location
and lift them over the old trees located on the river bank. The
installation of this bridge was one of the first steps of the Nantes island
renewal project"
ATELIERS
ET CHANTIERS DU HAVRE
December
1999
Port
of Le Havre
ATELIERS ET CHANTIERS DU HAVRE
Handling
and installation of a living quarter of 420 tons
on the LNG carrier "STOLT PERSEVERENCE" using the
floating sheerleg TAKLIFT 7 of 1200 tons lifting
capacity.EIFFEL
October
1998
"Musée d'Orsay - Jardins des Tuileries" in Paris.
EIFFEL
Lifting
and installation across the Seine river of the pedestrian
bridge " SOLFERINO " using floating sheerleg "AMSTERDAM"
of 300 tons of lifting capacity.PORT
AUTONOME DE ROUEN
October
1996
Harbour
area of Rouen and Seine river up to Honfleur.
PORT AUTONOME DE ROUEN
Handling
and transfer from quay to quay of 4 harbour cranes
Using the floating crane "TAKLIFT 6" of 800 tons
lifting capacity.CAILLARD
April
1994
Ouistreham
Canal in Caen (France).
|
|
| GIANT
MARINE TRANSPORT S.A.R.L. 3 Rue du Maréchal de Lattre de Tassigny 78150 LE CHESNAY Tel.:+33 (0) 1 39 63 37 37 Fax: +33 (0) 1 39 55 81 49 |